  • Tailored large-size blowers based on precise design and manufacturing technology.

    We provide world-renowned ITO brand products and services with a time-proven business history for over 150 years.

English

Mission

Robust products that pursued
technology and performance

Customizing blowers constituting the core of large-scale plants such as exhaust gas/waste disposal facilities or petrochemical complexes, which will achieve high energy efficiency, functions, and quality to contribute to industrial innovation in society.

See Details

Customer deployments

Large number of track record in delivering products to countries
all over the world in addition to Japan domestic.

Since large-size blowers are essential equipment in various facilities and plants,
there is high demand globally. Our products are installed on all continents except Antarctica.

See Details
map
トップページ > English > List of Services

List of Maintenance Services

Service nameService content
Purchasing partsWe will reply quickly for quotation and delivery based on the information regarding model name and serial number of the blower.
Proposing maintenance plansBased on the results of disassembling, we will indicate the maintenance details with emphasis on “extending equipment life”, “avoiding accident risk” and “minimizing maintenance cost”.
Maintenance (Overhaul)
Please refer to the Table listed below (standard overhaul inspection content)
Simple inspectionPlease refer to the Table listed below (Simple inspection)
Emergency servicesEach sales branch office will respond to emergency call and dispatch a technician to users’ site in case it is necessary and feasible.
Dispatch of SupervisorIt is not impossible to provide guidance of working instruction at users’ site in case customers would operate the maintenance by themselves. But we cannot guarantee the outcome if our technician did not work it directly.




Standard overhaul inspection content

Service content    Service details      Special notes
1. Before work- Check of work content
1-1 Delivery of materials and tools- Materials and tools are carried in from designated area
- To organize them temporarily at working space.

  1-2 Preparation for work


- Curing the work area as necessary 
- Confirm subject devices
- Shut off the power supply- Request the customer to switch over
- Close the interlocking valve- Request the customer to switch over
 2. Maintenance workDisassemble, clean/replace parts, assemble, test run, and make a report- Bring back the drained oil as a waste oil

 2-1 Disassembly
- Dismount V-belt cover
- Remove V-beltIn case it is impossible to remove components due to deterioration or seizure, discuss with customer.
- Drain Oil (pulley and gear side)
- Remove Pulley
- Blower disassembly (oil case, side cover, bearing holder, rotor, inside of the casing, etc.)
 2-2 Cleaning
- Clean reusable parts (oil case, side cover, bearing holder, rotor, inside of the casing, etc.) 
- Bring back the drained oil as a waste oil
 2-3 Rust proof coating to inner parts and surface
- Apply SUS coating to the surface where contacting process gas.
- May not be applied depending on the blower specification
 2-4 Measurement
- Visual inspection (inner surface of the casing, rotor surface, timing gear contact surface, etc.)
 
- Rotor shaft surface at bearing mounted and oil seal gripped.
- Measured with a micrometer
 2-5 Assembly
- Rotor assembly, parts replacement, side cover, oil case assembly
 
- Clearance adjustment
 
- Install Pulley, belt (tension adjustment)
 
- Mount Belt cover
 
- Pour Oil 
3. Accessory inspection
- Suction silencer, filter, safety valve, pressure gauge, etc.
- Visual inspection to confirm no abnormality
4. Test run
- In principle, perform a test run for one hour
 
 4-1 Bearing temperature
- Measure four times in total every 15 minutes to confirm that there is no abnormality 
 4-2 Vibration
- Confirm that there is no abnormal vibration at the start of test running, and measure the vibration value just before finish the test.
 
 4-3 Noise
- Confirm that there is no abnormal noise
 
 4-4 Oil leakage- Confirm that there is no leakage from the shaft penetrating bore and the matching surfaces of each part
 
5. After work
- Report the completion of work to the client
 
 5-1 Cleaning up- Organize and clean the work area
 
 5-2 Moving out materials and tools- Carry materials and tools out of designated area 
6. Report
- In principle, submit report within two weeks after the work completion 
 6-1 - Photos basically contain followings;
- In principle, the maintenance photos submitted are as follows.
(1) Before the work
(2) Overhaul inspection
(3) During cleaning
(4) Replaced parts (new/old)
(5) During assembly
(6) Assembly completion
(7) Test run
(8) Completion
 
7. Warranty
- One year warranty in accordance with our company regulations
 



Simple inspection

Service contentService detailsSpecial notes
1. Before work- Confirm work content
 1-1 Moving out materials and tools- Materials and tools are carried in from designated area
- To organize them temporarily at working space.

 1-2 Preparation for work


- Curing the work area as necessary

- Confirm subject devices
- Shut off the power supply- Request the customer to switch over
- Close the interlocking valve- Request the customer to switch over
2. Simple inspection work
- Visual inspection and oil/V-belt replacement. 
 2-1 Visual inspection of internal components- Check the internal condition of the blower visually from the suction side nozzle.
 
- Confirm clearance
 
 2-2 Oil, belt inspection- Dismount V-belt cover 
- Remove V-belt
 
- Drain Oil (pulley and gear side)
 
- Pour new Oil and install V-belt
 
3. Accessory inspection
- Suction silencer, filter, safety valve, pressure gauge, etc.
- Visual inspection to confirm no abnormality
4. Test run
- In principle, perform a test run for one hour
 
 4-1 Bearing temperature- Measure four times in total every 15 minutes to confirm that there is no abnormality
 
 4-2 Vibration
- Confirm that there is no abnormal vibration at the start of test running, and measure the vibration value just before finish the test.
 
 4-3 Noise
- Confirm that there is no abnormal noise
 
 4-4 Oil leakage- Confirm that there is no leakage from the shaft penetrating bore and the matching surfaces of each part
 
5. After work
- Report the completion of work to the client
 
 5-1 Cleaning up- Organize and clean the work area 
 5-2 Moving out materials and tools- Carry materials and tools out of designated area 
6. Report- In principle, submit report within two weeks after the work completion
 
7. Warranty
- There is no warranty because no wear-out components in the blower replaced
 